BetaActiveSolarBatteryWAPA-DSWLBNL
160 MW hybrid in San Bernardino, CA · In queue since June 2019 · Proposed COD December 2021
160 MW
Capacity
1
Components
Solar
6y 9m
In Queue
—
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
2y 6m
Schedule
53 months past proposed COD
Pre-Study0%
Queue EntryJun 27, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-12-01
Project Details
State
CA
County
San Bernardino
Region
West
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Point of Interconnection
Headgate-Blythe
Data Source
LBNL
No news available for this project.