— Project Summary

Queue ID
TVA-672
Capacity
140 MW
Technology
Solar
Status
active
Location
Rankin, MS
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarTVALBNL

140 MW generation in Rankin, MS · In queue since October 2024 · Proposed COD September 2027

140 MW

Capacity

1

Components

Solar

1y 5m

In Queue

Cluster Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

2y 11m

Impact Study25%
Queue EntryOct 30, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-01

Project Details

State

MS

County

Rankin

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

TVA's Sebastopol-Leake 161kV TL

Data Source

LBNL