BetaActiveSolarTVALBNL
150 MW generation in Lawrence, AL · In queue since October 2024 · Proposed COD February 2026
150 MW
Capacity
1
Components
Solar
1y 5m
In Queue
Cluster Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
1y 4m
Schedule
2 months past proposed COD
Impact Study25%
Queue EntryOct 4, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-02-06
Project Details
State
AL
County
Lawrence
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Wheeler-Trinty 161kV TL
Data Source
LBNL
No news available for this project.