— Project Summary

Queue ID
TVA-667
Capacity
150 MW
Technology
Solar
Status
active
Location
Lawrence, AL
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarTVALBNL

150 MW generation in Lawrence, AL · In queue since October 2024 · Proposed COD February 2026

150 MW

Capacity

1

Components

Solar

1y 5m

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

1y 4m

Schedule

2 months past proposed COD

Impact Study25%
Queue EntryOct 4, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-02-06

Project Details

State

AL

County

Lawrence

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Wheeler-Trinty 161kV TL

Data Source

LBNL

No news available for this project.