BetaActiveBatteryTVALBNL
200 MW storage in Shelby, TN · In queue since October 2024 · Proposed COD April 2026
200 MW
Capacity
1
Components
Battery
1y 5m
In Queue
Cluster Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
1y 6m
Impact Study25%
Queue EntryOct 1, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-04-30
Project Details
State
TN
County
Shelby
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
TVA's Allen _x0013_ Freeport 161kV TL
Data Source
LBNL