BetaActiveSolarTVALBNL
99 MW generation in Jackson, AL · In queue since October 2024 · Proposed COD October 2032
99 MW
Capacity
1
Components
Solar
1y 5m
In Queue
Cluster Study
IA Status
COD target: 2032
Interconnection Timeline
Total Duration
8 years
Impact Study25%
Queue EntryOct 1, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2032-10-30
Project Details
State
AL
County
Jackson
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Widow's Creek 161 kV Switchyard
Data Source
LBNL
No news available for this project.