— Project Summary

Queue ID
TVA-658
Capacity
7 MW
Technology
Hydro
Status
active
Location
Loudon, TN
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveHydroTVALBNL

7 MW generation in Loudon, TN · In queue since October 2024

7 MW

Capacity

1

Components

Hydro

1y 5m

In Queue

Cluster Study

IA Status

Interconnection Timeline

Total Duration

1y 5m

Impact Study25%
Queue EntryOct 1, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

TN

County

Loudon

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Ft. Loudon Hydro Bus 364422

Data Source

LBNL

No news available for this project.