— Project Summary

Queue ID
TVA-644
Capacity
150 MW
Technology
Solar
Status
active
Location
Obion, TN
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarTVALBNL

150 MW generation in Obion, TN · In queue since September 2024 · Proposed COD January 2028

150 MW

Capacity

1

Components

Solar

1y 6m

In Queue

Cluster Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 4m

Impact Study25%
Queue EntrySep 6, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-01-07

Project Details

State

TN

County

Obion

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

TVA's N. Union City - Woodland Mills 161 kV TL

Data Source

LBNL

No news available for this project.