BetaActiveSolarTVALBNL
150 MW generation in Obion, TN · In queue since September 2024 · Proposed COD January 2028
150 MW
Capacity
1
Components
Solar
1y 6m
In Queue
Cluster Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 4m
Impact Study25%
Queue EntrySep 6, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-01-07
Project Details
State
TN
County
Obion
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
TVA's N. Union City - Woodland Mills 161 kV TL
Data Source
LBNL
No news available for this project.