100 MW generation in Jackson, AL · In queue since August 2024 · Proposed COD August 2029
100 MW
Capacity
1
Components
Solar
1y 7m
In Queue
Cluster Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5 years
Impact Study25%
Queue EntryAug 28, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-08-01
Project Details
State
AL
County
Jackson
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Widow_x0019_s Creek FP _x0013_ Bellefonte NP 161kv TL
Data Source
LBNL