BetaActiveNuclearTVALBNL
24 MW generation in Hamilton, TN · In queue since August 2024 · Proposed COD November 2027
24 MW
Capacity
1
Components
Nuclear
1y 7m
In Queue
Cluster Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 3m
Impact Study25%
Queue EntryAug 14, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-11-05
Project Details
State
TN
County
Hamilton
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
SQN 500kV Switchyard
Data Source
LBNL