— Project Summary

Queue ID
TVA-632
Capacity
69 MW
Technology
Solar
Status
active
Location
Oktibbeha, MS
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarTVALBNL

69 MW generation in Oktibbeha, MS · In queue since June 2024 · Proposed COD October 2028

69 MW

Capacity

1

Components

Solar

1y 9m

In Queue

Cluster Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 4m

Impact Study25%
Queue EntryJun 28, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-12

Project Details

State

MS

County

Oktibbeha

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

U Cement Tap - Holman MS 161 kV TL

Data Source

LBNL

No news available for this project.