BetaActiveGasTVALBNL
1,600 MW generation in Todd, KY · In queue since June 2024 · Proposed COD June 2030
1,600 MW
Capacity
1
Components
Gas
1y 9m
In Queue
Cluster Study
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
6 years
Impact Study25%
Queue EntryJun 12, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-06-01
Project Details
State
KY
County
Todd
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
PARADISE - MONTGOMERY 500 KV
Data Source
LBNL