— Project Summary

Queue ID
TVA-628
Capacity
1600 MW
Technology
Gas
Status
active
Location
Todd, KY
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveGasTVALBNL

1,600 MW generation in Todd, KY · In queue since June 2024 · Proposed COD June 2030

1,600 MW

Capacity

1

Components

Gas

1y 9m

In Queue

Cluster Study

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

6 years

Impact Study25%
Queue EntryJun 12, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-06-01

Project Details

State

KY

County

Todd

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

PARADISE - MONTGOMERY 500 KV

Data Source

LBNL

No news available for this project.