BetaActiveNuclearTVALBNL
25 MW generation in Hamilton, TN · In queue since June 2024 · Proposed COD December 2028
25 MW
Capacity
1
Components
Nuclear
1y 9m
In Queue
Cluster Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 6m
Impact Study25%
Queue EntryJun 12, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
TN
County
Hamilton
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Existing
Data Source
LBNL
No news available for this project.