BetaActiveGasTVALBNL
1,600 MW generation in Trousdale, TN · In queue since June 2024 · Proposed COD June 2031
1,600 MW
Capacity
1
Components
Gas
1y 9m
In Queue
Cluster Study
IA Status
COD target: 2031
Interconnection Timeline
Total Duration
7 years
Impact Study25%
Queue EntryJun 12, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2031-06-01
Project Details
State
TN
County
Trousdale
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
New Central Region Gas Plant
Data Source
LBNL
No news available for this project.