BetaActiveGasTVALBNL
800 MW generation in Stewart, TN · In queue since June 2024 · Proposed COD June 2027
800 MW
Capacity
1
Components
Gas
1y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3 years
Facilities Study50%
Queue EntryJun 12, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
TN
County
Stewart
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Cumberland CC 500kV SS
Data Source
LBNL
No news available for this project.