— Project Summary

Queue ID
TVA-611
Capacity
100 MW
Technology
Solar
Status
active
Location
Maury, TN
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveSolarTVALBNL

100 MW generation in Maury, TN · In queue since March 2024 · Proposed COD April 2027

100 MW

Capacity

1

Components

Solar

2 years

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 1m

Facilities Study50%
Queue EntryMar 25, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-15

Project Details

State

TN

County

Maury

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Mt. Pleasant 161kV substation

Data Source

LBNL

No news available for this project.