BetaActiveSolarTVALBNL
100 MW generation in Maury, TN · In queue since March 2024 · Proposed COD April 2027
100 MW
Capacity
1
Components
Solar
2 years
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 1m
Facilities Study50%
Queue EntryMar 25, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-15
Project Details
State
TN
County
Maury
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Mt. Pleasant 161kV substation
Data Source
LBNL
No news available for this project.