200 MW generation in Monroe, MS · In queue since January 2024 · Proposed COD August 2028
200 MW
Capacity
1
Components
Solar
2y 2m
In Queue
Cluster Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 7m
Impact Study25%
Queue EntryJan 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-08-01
Project Details
State
MS
County
Monroe
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
TVA's Stateline-West Point 161 kV TL
Data Source
LBNL