— Project Summary

Queue ID
TVA-606
Capacity
200 MW
Technology
Solar
Status
active
Location
Monroe, MS
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarTVALBNL

200 MW generation in Monroe, MS · In queue since January 2024 · Proposed COD August 2028

200 MW

Capacity

1

Components

Solar

2y 2m

In Queue

Cluster Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 7m

Impact Study25%
Queue EntryJan 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-08-01

Project Details

State

MS

County

Monroe

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

TVA's Stateline-West Point 161 kV TL

Data Source

LBNL

No news available for this project.