BetaActiveBatteryTVALBNL
200 MW storage in Clay, MS · In queue since December 2023 · Proposed COD August 2026
200 MW
Capacity
1
Components
Battery
2y 3m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 8m
Facilities Study50%
Queue EntryDec 10, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-08-01
Project Details
State
MS
County
Clay
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
West Point, MS 500-kV Substation (161-kV)
Data Source
LBNL