— Project Summary

Queue ID
TVA-600
Capacity
200 MW
Technology
Battery
Status
active
Location
Clay, MS
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveBatteryTVALBNL

200 MW storage in Clay, MS · In queue since December 2023 · Proposed COD August 2026

200 MW

Capacity

1

Components

Battery

2y 3m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 8m

Facilities Study50%
Queue EntryDec 10, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-08-01

Project Details

State

MS

County

Clay

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

West Point, MS 500-kV Substation (161-kV)

Data Source

LBNL

No news available for this project.