— Project Summary

Queue ID
TVA-593
Capacity
500 MW
Technology
Solar+Battery
Status
active
Location
Mississippi, AR
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveSolarBatteryTVALBNL

500 MW hybrid in Mississippi, AR · In queue since December 2023 · Proposed COD March 2027

500 MW

Capacity

1

Components

Solar

2y 3m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 3m

Facilities Study50%
Queue EntryDec 1, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-03-15

Project Details

State

AR

County

Mississippi

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Shelby, TN 500 KV SS

Data Source

LBNL

No news available for this project.