BetaActiveSolarBatteryTVALBNL
500 MW hybrid in Mississippi, AR · In queue since December 2023 · Proposed COD March 2027
500 MW
Capacity
1
Components
Solar
2y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 3m
Facilities Study50%
Queue EntryDec 1, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-03-15
Project Details
State
AR
County
Mississippi
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Shelby 500kV SS
Data Source
LBNL