BetaActiveHydroTVALBNL
7 MW generation in Marion, AL · In queue since November 2023
7 MW
Capacity
1
Components
Hydro
2y 4m
In Queue
Cluster Study
IA Status
Interconnection Timeline
Total Duration
2y 4m
Impact Study25%
Queue EntryNov 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
AL
County
Marion
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Nickajack Dam
Data Source
LBNL
No news available for this project.