238 MW generation in Shelby, TN · In queue since November 2023 · Proposed COD October 2024
238 MW
Capacity
1
Components
Gas
2y 4m
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
11 months
Schedule
18 months past proposed COD
Facilities Study50%
Queue EntryNov 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-10-01
Project Details
State
TN
County
Shelby
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
L5396, Str 8 - Allen CCP
Data Source
LBNL
No news available for this project.