— Project Summary

Queue ID
TVA-588
Capacity
238 MW
Technology
Gas
Status
active
Location
Shelby, TN
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveGasTVALBNL

238 MW generation in Shelby, TN · In queue since November 2023 · Proposed COD October 2024

238 MW

Capacity

1

Components

Gas

2y 4m

In Queue

Facility Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

11 months

Schedule

18 months past proposed COD

Facilities Study50%
Queue EntryNov 3, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-10-01

Project Details

State

TN

County

Shelby

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

L5396, Str 8 - Allen CCP

Data Source

LBNL

No news available for this project.