— Project Summary

Queue ID
TVA-587
Capacity
225 MW
Technology
Battery
Status
active
Location
Hawkins, TN
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveBatteryTVALBNL

225 MW storage in Hawkins, TN · In queue since October 2023 · Proposed COD March 2029

225 MW

Capacity

1

Components

Battery

2y 5m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 5m

Facilities Study50%
Queue EntryOct 11, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-03-01

Project Details

State

TN

County

Hawkins

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Phipps Bend 500 kV TL

Data Source

LBNL

No news available for this project.