— Project Summary

Queue ID
TVA-586
Capacity
20 MW
Technology
Battery
Status
active
Location
Wayne, TN
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveBatteryTVALBNL

20 MW storage in Wayne, TN · In queue since October 2023 · Proposed COD March 2029

20 MW

Capacity

1

Components

Battery

2y 5m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 5m

Facilities Study50%
Queue EntryOct 11, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-03-01

Project Details

State

TN

County

Wayne

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Waynesboro City - Clifton City 69 kV TL

Data Source

LBNL

No news available for this project.