BetaActiveSolarTVALBNL
220 MW generation in Chickasaw, MS · In queue since September 2023 · Proposed COD May 2027
220 MW
Capacity
1
Components
Solar
2y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 8m
Facilities Study50%
Queue EntrySep 19, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-05-10
Project Details
State
MS
County
Chickasaw
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
TVA's Okolona - Calhoun City 161 kV TL
Data Source
LBNL
No news available for this project.