— Project Summary

Queue ID
TVA-569
Capacity
620 MW
Technology
Gas
Status
active
Location
Lowndes, MS
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveGasTVALBNL

620 MW generation in Lowndes, MS · In queue since June 2023 · Proposed COD September 2026

620 MW

Capacity

1

Components

Gas

2y 9m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 3m

Facilities Study50%
Queue EntryJun 20, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-09-01

Project Details

State

MS

County

Lowndes

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Lowndes 161kV Substation

Data Source

LBNL