— Project Summary

Queue ID
TVA-567
Capacity
990 MW
Technology
Gas
Status
active
Location
Cheatham, TN
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveGasTVALBNL

990 MW generation in Cheatham, TN · In queue since June 2023 · Proposed COD September 2027

990 MW

Capacity

1

Components

Gas

2y 9m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 3m

Facilities Study50%
Queue EntryJun 16, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-01

Project Details

State

TN

County

Cheatham

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

DAVIDSON - MONTGOMERY 500 KV TL

Data Source

LBNL

No news available for this project.