— Project Summary

Queue ID
TVA-540
Capacity
150 MW
Technology
Solar
Status
active
Location
Chickasaw, MS
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveSolarTVALBNL

150 MW generation in Chickasaw, MS · In queue since April 2023 · Proposed COD November 2029

150 MW

Capacity

1

Components

Solar

2y 11m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

6y 7m

Facilities Study50%
Queue EntryApr 5, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-11-13

Project Details

State

MS

County

Chickasaw

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Okolona - Calhoun City 161kV TL

Data Source

LBNL

No news available for this project.