BetaActiveSolarTVALBNL
150 MW generation in Chickasaw, MS · In queue since April 2023 · Proposed COD November 2029
150 MW
Capacity
1
Components
Solar
2y 11m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
6y 7m
Facilities Study50%
Queue EntryApr 5, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-11-13
Project Details
State
MS
County
Chickasaw
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Okolona - Calhoun City 161kV TL
Data Source
LBNL
No news available for this project.