150 MW hybrid in Henderson, TN · In queue since March 2023 · Proposed COD April 2029
150 MW
Capacity
1
Components
Solar
3 years
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
6y 1m
Facilities Study50%
Queue EntryMar 28, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-04-24
Project Details
State
TN
County
Henderson
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Johnsonville Steam - Chesterfield 161-kV TL
Data Source
LBNL
No news available for this project.