— Project Summary

Queue ID
TVA-536
Capacity
350 MW
Technology
Solar
Status
active
Location
Muhlenberg, KY
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveSolarTVALBNL

350 MW generation in Muhlenberg, KY · In queue since March 2023 · Proposed COD August 2026

350 MW

Capacity

1

Components

Solar

3 years

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 5m

Facilities Study50%
Queue EntryMar 28, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-08-11

Project Details

State

KY

County

Muhlenberg

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Lost City, KY 161-kV Switching Station

Data Source

LBNL

No news available for this project.