BetaActiveSolarBatteryTVALBNL
135 MW hybrid in Marshall, TN · In queue since March 2023 · Proposed COD May 2028
135 MW
Capacity
1
Components
Solar
3 years
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 2m
Facilities Study50%
Queue EntryMar 22, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-30
Project Details
State
TN
County
Marshall
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
TVA_x0019_s Franklin-Belfast 161-kV Transmission Line
Data Source
LBNL
No news available for this project.