— Project Summary

Queue ID
TVA-532
Capacity
50 MW
Technology
Solar+Battery
Status
active
Location
Chickasaw, MS
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveSolarBatteryTVALBNL

50 MW hybrid in Chickasaw, MS · In queue since March 2023 · Proposed COD August 2024

50 MW

Capacity

1

Components

Solar

3 years

In Queue

Facility Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

1y 5m

Schedule

20 months past proposed COD

Facilities Study50%
Queue EntryMar 15, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-08-01

Project Details

State

MS

County

Chickasaw

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Clay - Okolona 161-kV TL

Data Source

LBNL

No news available for this project.