50 MW hybrid in Chickasaw, MS · In queue since March 2023 · Proposed COD August 2024
50 MW
Capacity
1
Components
Solar
3 years
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 5m
Schedule
20 months past proposed COD
Facilities Study50%
Queue EntryMar 15, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-08-01
Project Details
State
MS
County
Chickasaw
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Clay - Okolona 161-kV TL
Data Source
LBNL