50 MW generation in Marshall, MS · In queue since September 2022 · Proposed COD December 2029
50 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
7y 3m
Facilities Study50%
Queue EntrySep 2, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-14
Project Details
State
MS
County
Marshall
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Holly Springs - Chickasaw Trail IP 161-kV TL
Data Source
LBNL
No news available for this project.