BetaActiveSolarBatteryTVALBNL
120 MW hybrid in Graves, KY · In queue since August 2022 · Proposed COD March 2029
120 MW
Capacity
1
Components
Solar
3y 7m
In Queue
IA Executed
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
6y 7m
Construction75%
Queue EntryAug 31, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2029-03-16
Project Details
State
KY
County
Graves
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Paris - Mayfield No1 & No2 161kV TL
Data Source
LBNL
No news available for this project.