BetaActiveSolarBatteryTVALBNL
150 MW hybrid in Lauderdale, AL · In queue since August 2022 · Proposed COD January 2029
150 MW
Capacity
1
Components
Solar
3y 7m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
6y 5m
Facilities Study50%
Queue EntryAug 26, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-01-24
Project Details
State
AL
County
Lauderdale
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Wheeler HP-Elgin-Mt Pleasant No 1 161-kV TL
Data Source
LBNL