BetaActiveSolarTVALBNL
200 MW generation in Lee, MS · In queue since August 2022 · Proposed COD December 2028
200 MW
Capacity
1
Components
Solar
3y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 4m
Facilities Study50%
Queue EntryAug 23, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-11
Project Details
State
MS
County
Lee
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Union - Tupelo No. 3 161-kV TL
Data Source
LBNL
No news available for this project.