— Project Summary

Queue ID
TVA-504
Capacity
70 MW
Technology
Solar
Status
active
Location
Chickasaw, MS
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveSolarTVALBNL

70 MW generation in Chickasaw, MS · In queue since June 2022 · Proposed COD July 2028

70 MW

Capacity

1

Components

Solar

3y 9m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

6y 1m

Facilities Study50%
Queue EntryJun 20, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-07-28

Project Details

State

MS

County

Chickasaw

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Okolona - Clay 161-kV TL

Data Source

LBNL