BetaActiveSolarTVALBNL
70 MW generation in Gibson, TN · In queue since June 2022 · Proposed COD November 2024
70 MW
Capacity
1
Components
Solar
3y 9m
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 5m
Schedule
17 months past proposed COD
Facilities Study50%
Queue EntryJun 20, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-11-08
Project Details
State
TN
County
Gibson
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Weakley - Dyersburg No1 161-kV TL
Data Source
LBNL