— Project Summary

Queue ID
TVA-483
Capacity
1600 MW
Technology
Gas
Status
active
Location
Stewart, TN
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveGasTVALBNL

1,600 MW generation in Stewart, TN · In queue since October 2021 · Proposed COD September 2025

1,600 MW

Capacity

1

Components

Gas

4y 5m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 11m

Schedule

7 months past proposed COD

Facilities Study50%
Queue EntryOct 8, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-09-01

Project Details

State

TN

County

Stewart

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Cumberland 500-kV Switchyard

Data Source

LBNL

No news available for this project.