— Project Summary

Queue ID
TVA-477
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Hardeman, TN
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarBatteryTVALBNL

200 MW hybrid in Hardeman, TN · In queue since June 2021 · Proposed COD August 2029

200 MW

Capacity

1

Components

Solar

4y 9m

In Queue

IA Executed

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

8y 2m

Construction75%
Queue EntryJun 8, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2029-08-07

Project Details

State

TN

County

Hardeman

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Selmer - Bolivar 161-kV TL Cordova - Hickory Valley No 2 161-kV TL

Data Source

LBNL