36 MW generation in Lyon, KY · In queue since April 2021 · Proposed COD August 2022
36 MW
Capacity
1
Components
Hydro
4y 11m
In Queue
Facility Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 4m
Schedule
44 months past proposed COD
Facilities Study50%
Queue EntryApr 29, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-08-01
Project Details
State
KY
County
Lyon
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Barkley Power Plant
Data Source
LBNL