BetaActiveNuclearTVALBNL
9 MW generation in Hamilton, TN · In queue since March 2021 · Proposed COD November 2022
9 MW
Capacity
1
Components
Nuclear
5 years
In Queue
IA Executed
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 8m
Schedule
41 months past proposed COD
Construction75%
Queue EntryMar 30, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 60–120 months
Commercial Operation
Proposed COD: 2022-11-06
Project Details
State
TN
County
Hamilton
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Sequoyah Nuclear 500-kV Substation
Data Source
LBNL
No news available for this project.