BetaActiveSolarBatteryTVALBNL
125 MW hybrid in Henderson, TN · In queue since March 2021 · Proposed COD November 2028
125 MW
Capacity
1
Components
Solar
5 years
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 8m
Construction75%
Queue EntryMar 23, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2028-11-27
Project Details
State
TN
County
Henderson
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Johnsonville FP - S Jackson 161-kV TL
Data Source
LBNL