BetaActiveSolarTVALBNL
200 MW generation in Clay, MS · In queue since February 2021 · Proposed COD June 2028
200 MW
Capacity
1
Components
Solar
5y 1m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 4m
Construction75%
Queue EntryFeb 8, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-06-12
Project Details
State
MS
County
Clay
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
West Point, MS 500-kV Substation (161-kV)
Data Source
LBNL
No news available for this project.