— Project Summary

Queue ID
TVA-466
Capacity
200 MW
Technology
Solar
Status
active
Location
Clay, MS
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarTVALBNL

200 MW generation in Clay, MS · In queue since February 2021 · Proposed COD June 2028

200 MW

Capacity

1

Components

Solar

5y 1m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

7y 4m

Construction75%
Queue EntryFeb 8, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-06-12

Project Details

State

MS

County

Clay

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

West Point, MS 500-kV Substation (161-kV)

Data Source

LBNL

No news available for this project.