BetaActiveSolarTVALBNL
127 MW generation in Lowndes, MS · In queue since July 2020 · Proposed COD March 2028
127 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 8m
Construction75%
Queue EntryJul 1, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-03-06
Project Details
State
MS
County
Lowndes
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Lowndes, MS 500-kV Substation
Data Source
LBNL
No news available for this project.