200 MW generation in Moore, TN · In queue since June 2020 · Proposed COD September 2025
200 MW
Capacity
1
Components
Solar
5y 9m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
5y 3m
Schedule
7 months past proposed COD
Construction75%
Queue EntryJun 22, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-09-02
Project Details
State
TN
County
Moore
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Franklin - Warchase No 2 161-kV TL
Data Source
LBNL