BetaActiveBatteryTVALBNL
200 MW storage in Clay, MS · In queue since April 2020 · Proposed COD November 2027
200 MW
Capacity
1
Components
Battery
5y 11m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 7m
Construction75%
Queue EntryApr 29, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2027-11-12
Project Details
State
MS
County
Clay
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
West Point 161-kV Substation
Data Source
LBNL
No news available for this project.