— Project Summary

Queue ID
TVA-425
Capacity
150 MW
Technology
Solar
Status
active
Location
Chickasaw, MS
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveSolarTVALBNL

150 MW generation in Chickasaw, MS · In queue since April 2020 · Proposed COD March 2028

150 MW

Capacity

1

Components

Solar

5y 11m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

7y 11m

Facilities Study50%
Queue EntryApr 23, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-03-08

Project Details

State

MS

County

Chickasaw

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Clay - Okolona 161-kV TL

Data Source

LBNL

No news available for this project.