— Project Summary

Queue ID
TVA-424
Capacity
50 MW
Technology
Battery
Status
active
Location
Clay, MS
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveBatteryTVALBNL

50 MW storage in Clay, MS · In queue since April 2020 · Proposed COD May 2025

50 MW

Capacity

1

Components

Battery

5y 11m

In Queue

IA Executed

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

5y 1m

Schedule

11 months past proposed COD

Construction75%
Queue EntryApr 21, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2025-05-08

Project Details

State

MS

County

Clay

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

West Point 161-kV Substation

Data Source

LBNL