BetaActiveSolarTVALBNL
145 MW generation in Chickasaw, MS · In queue since April 2020 · Proposed COD August 2026
145 MW
Capacity
1
Components
Solar
5y 11m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
6y 4m
Construction75%
Queue EntryApr 2, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-08-28
Project Details
State
MS
County
Chickasaw
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Okolona 161-kV Substation
Data Source
LBNL