BetaActiveSolarTVALBNL
66 MW generation in Lawrence, AL · In queue since March 2020 · Proposed COD October 2024
66 MW
Capacity
1
Components
Solar
6 years
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
4y 7m
Schedule
18 months past proposed COD
Facilities Study50%
Queue EntryMar 25, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-10-15
Project Details
State
AL
County
Lawrence
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Colbert FP - Wheeler HP 161-kV TL
Data Source
LBNL
No news available for this project.