— Project Summary

Queue ID
TVA-420
Capacity
66 MW
Technology
Solar
Status
active
Location
Lawrence, AL
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveSolarTVALBNL

66 MW generation in Lawrence, AL · In queue since March 2020 · Proposed COD October 2024

66 MW

Capacity

1

Components

Solar

6 years

In Queue

Facility Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

4y 7m

Schedule

18 months past proposed COD

Facilities Study50%
Queue EntryMar 25, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-10-15

Project Details

State

AL

County

Lawrence

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Colbert FP - Wheeler HP 161-kV TL

Data Source

LBNL

No news available for this project.